I am putting in the plumbing under the slab in my workshop. I am doing some floor drains in a few different places and wanted to confirm my plan before proceeding. I made a quick sketch of the layout but there seems to be a problem posting pictures on this site right now.
My questions are this:
1. I was told to put all schedule 40 under the slab. I later realized that my hardware store carries both schedule 40 couplers and DWV couplers. However, all the wyes, tees, specialty fittings etc are simply marked DWV. Are these appropriate for under slab?
2. I was going to dig the trenches for the PVC and then embed them in AB3. This is simply how I did all my drainage pipe, is this still appropriate for this application or do I need to switch to a different gravel type?
3. I have gotten a LOT of warnings about potential blockages in an under-concrete P-trap for a floor drain. There is one drain that could get some sediment, and I was planning on making a small "pit" with a grate for sediment collection. I figured that in this pit, I could put a drain stub up, along with a stub up (with cap) on the other side of the trap to give access to both sides. I am hoping this makes any clog in the trap clearable?
4. Are these drains ok for the lower usage areas that shouldn't get any sediment? I am also making sure these are suitable to embed in a 6" pour. Floor drain with integrated cleanout
5. Since I can't post a picture, this makes it a little more difficult to explain, but in short, I have a main 3" trunk that run about 50 feet (with a 45 here and there). One end terminates in the sewer, the other end sweeps up with a cleanout and vent to the roof. The trunk has 4 branches, one 3" for the big drain mentioned before, and three 2" branches for your typical drain/cleanout floor drains. I was under the impression that as long as a branch is less than 15' from the main trunk, it does NOT need any additional venting, is this correct?
My questions are this:
1. I was told to put all schedule 40 under the slab. I later realized that my hardware store carries both schedule 40 couplers and DWV couplers. However, all the wyes, tees, specialty fittings etc are simply marked DWV. Are these appropriate for under slab?
2. I was going to dig the trenches for the PVC and then embed them in AB3. This is simply how I did all my drainage pipe, is this still appropriate for this application or do I need to switch to a different gravel type?
3. I have gotten a LOT of warnings about potential blockages in an under-concrete P-trap for a floor drain. There is one drain that could get some sediment, and I was planning on making a small "pit" with a grate for sediment collection. I figured that in this pit, I could put a drain stub up, along with a stub up (with cap) on the other side of the trap to give access to both sides. I am hoping this makes any clog in the trap clearable?
4. Are these drains ok for the lower usage areas that shouldn't get any sediment? I am also making sure these are suitable to embed in a 6" pour. Floor drain with integrated cleanout
5. Since I can't post a picture, this makes it a little more difficult to explain, but in short, I have a main 3" trunk that run about 50 feet (with a 45 here and there). One end terminates in the sewer, the other end sweeps up with a cleanout and vent to the roof. The trunk has 4 branches, one 3" for the big drain mentioned before, and three 2" branches for your typical drain/cleanout floor drains. I was under the impression that as long as a branch is less than 15' from the main trunk, it does NOT need any additional venting, is this correct?