Zxed
Member
Building a new house, the plumber decided to move the toilet drain due to footing, instead of moving it back, he moved it left, which brought it closer to shower, but he forgot to adjust the shower drain.
We’re wrapping up framing and I’m trying to figure out what to tell them.
I can avoid jogging the wall by using a wall mount as long as there is enough room as there is a 2” pipe next to the 4” toilet drain. Not sure what it’s for. Maybe vent?
The shower one is the issue.
Is the only option to cut into slub and Move shower?