Re: Remodeling Bathroom
Posted by Hube on February 25, 2003 at 09:30:03:
In response to Re: Remodeling Bathroom
: I'm currently remodeling my bathroom. I have completely stripped all walls, fixtures and wiring out. I have replaced the walls with drywall and I'm almost ready to paint them. All wiring is pulled to new boxes.

: My question is, what order should I do the tasks I have left?

: Unlayment of the floor and tile.
: Install stand-up shower (plumbing and flooring under the shower is in place)
: Paint all walls and ceiling.
: Install toilet and pedestal sink. (I figured this would be last)

: Did I forget anything? (that you can tell?)

The order you list looks OK. Don't overlook a rough-in for exh. fan.(unless you have one).. good luck Hube