Re: New Tub Drain
Posted by Dales plumbing service on April 24, 1999 at 00:06:42:
In response to Re: New Tub Drain
: I recently broke up my basement concrete floor to move the toilet and tub drains. The builder had reinforced wires and a layer of poly about 4" down. Is there anything special I need to do when I pour new concrete? Is Sackrete/quickrete okay for the floor? In addition, I did not move the original p-trap for the tub drain. Will this cause any problems? The tub will be about 4' from the original location of the drain. I will have a rise of about 1" per foot of run.

: Thank you in advance!

: John Merrill
John, you need to cap off the old tub waste. just cut out the p trap and cap. you need to vent the new tub waste. you have to much grade on the pipe 1" per 4' is all that is required. the closet bend will be pretty crooked comeing up for the stool flange unless you put a swing joint on it.are you still within 8 feet of the original 2" vent for the stool?Dale



Replies to this post