Removed old steel tub and have temporarily installed drain.
Old tub was 30" x 60" new tub is 32" x 60". Installation is on a concrete slab which appears to be level. Old tub was resting on floor.
This is an alcove installation and the tub has a skirt.
A couple of questions: is there anything I should know before I slide this 350lbs tub into place? Walls are down to studs.
Also - getting ahead of myself - when installing the cement board "Durock" over the tub flang do I bring the board down far enough to cover tub flange and come into contact with and rest on the tub's flat surface? Also, is the smooth surface of the cemet board what you see after it's installed or is the rough surface left exposed?
Thanks, JM
Old tub was 30" x 60" new tub is 32" x 60". Installation is on a concrete slab which appears to be level. Old tub was resting on floor.
This is an alcove installation and the tub has a skirt.
A couple of questions: is there anything I should know before I slide this 350lbs tub into place? Walls are down to studs.
Also - getting ahead of myself - when installing the cement board "Durock" over the tub flang do I bring the board down far enough to cover tub flange and come into contact with and rest on the tub's flat surface? Also, is the smooth surface of the cemet board what you see after it's installed or is the rough surface left exposed?
Thanks, JM