(206) 949-5683, Top Rated Plumber, Seattle
Page 1 of 2 12 LastLast
Results 1 to 15 of 20

Thread: plumbing a toilet on an uneven floor?

  1. #1
    DIY Member pronouncedeyen's Avatar
    Join Date
    Sep 2009
    Location
    Baltimore, MD
    Posts
    46

    Default plumbing a toilet on an uneven floor?

    I'm rehabbing an old house and turning a small bedroom into a master bathroom and we're leaving the hardwood floor (don't ask!). The spot for the toilet is at the edge of the room where there is a significant amount of settling. From the left side of the toilet base to the right the floor drops about 3/4". So, the questions:

    - should I mount the toilet flange flush to the floor or should I shim up the right side?

    - if flush to the floor, then how do I make the toilet level? how do I make one side of the wax ring thicker than the other?

    - besides fashioning a wood base to fit the underside of the toilet base is there any way to make this look normal? My carpentry skills are limited at best so I was hoping for a solution that didn't involve a band saw. Maybe shim up the right side and fill the space with fast setting joint compound? Will that fill 3/4"?

  2. #2
    In the Trades Gary Swart's Avatar
    Join Date
    Sep 2004
    Location
    Yakima WA
    Posts
    7,246

    Default

    A 3/4" drop across the width of a toilet indicates a huge structural problem. I won't ask why you choose not to deal with it, but I can tell you that everything you have suggested would be look like hack job with doubtful success. You can put all the lipstick in the world on a pig, but when you're finished, it's still a pig. I realize this a very negative response to your question, but unless you deal with the cause of the problem, nothing is going to make this at all workable. Plumbers deal with slight variations in floors all of time with shims, but we're talking like 1/8" up to maybe 1/4". Leveling the floor is not a DIY job for a person with little or no carpentry skill and basic tools either.

  3. #3
    DIY scratch-pad engineer leejosepho's Avatar
    Join Date
    Nov 2006
    Location
    200 miles south of Little Rock
    Posts
    2,474

    Default

    Quote Originally Posted by pronouncedeyen View Post
    From the left side of the toilet base to the right the floor drops about 3/4". So, the questions:

    - should I mount the toilet flange flush to the floor or should I shim up the right side?
    The flange and toilet need to fit together properly, so the flange should be level with the toilet.

    Do you have any idea why that floor is not flat and level? Unless I have misunderstood, it seems odd to me that a floor would be low next to a wall unless you have balloon framing and the joist next to the wall might be rotted or loose or something. There is always a way to make something work out, but first the actual problem must be known.
    "Great minds discuss ideas, average minds discuss events and small minds discuss people." --Eleanor Roosevelt

  4. #4
    DIY Member pronouncedeyen's Avatar
    Join Date
    Sep 2009
    Location
    Baltimore, MD
    Posts
    46

    Default

    Thanks for the help guys. The house is brick and has settled towards the center of the house. The floor closest to the brick has settled the least. I always assumed this was because brick settles less than wood and the floor/beams/joists are attached to the brick so that part wouldn't settle near as much as the center of the house.

    Maybe I'll remeasure. The dip in the floor is present on all 3 floors of the house and it really isn't noticeable unless you're looking for it.

  5. #5
    DIY scratch-pad engineer leejosepho's Avatar
    Join Date
    Nov 2006
    Location
    200 miles south of Little Rock
    Posts
    2,474

    Default

    You could have a sagging beam down the center of the house, or possibly a settled footer under a post. I once had a situation like that, and it was really not that big of a job to jack things back up from below and keep them where they should be.
    "Great minds discuss ideas, average minds discuss events and small minds discuss people." --Eleanor Roosevelt

  6. #6
    In the Trades Gary Swart's Avatar
    Join Date
    Sep 2004
    Location
    Yakima WA
    Posts
    7,246

    Default

    The brick is resting on a concrete foundation and is not subject to settling. The sag in the center is due to failure of the interior supports. Can't be more specific than that with the information at hand. Up to you, but if it was mine I'd have a contractor examine the structure.

  7. #7
    DIY Senior Member wjcandee's Avatar
    Join Date
    Apr 2012
    Location
    New York, NY
    Posts
    1,590

    Default

    I would remeasure.

    The width of the base of a Toto original Drake, for example, is 9" or .75 feet. A 3/4-inch slope across the base divided by .75 means a slope left to right of one-inch-per-foot. If the room is 15 feet wide, the drop from left to right would be fifteen inches, or a foot-and-a-quarter. That would be noticeable to the naked eye, I would think.

    If the slope is more in the range of what Gary is talking about, then it's easy enough to shim the toilet. You don't need to money with the wax ring because you will get one that fills the gap on the long side and the other side will just smush around.

  8. #8
    In the Trades Gary Swart's Avatar
    Join Date
    Sep 2004
    Location
    Yakima WA
    Posts
    7,246

    Default

    Thanks wjcandee for doing what we all should have done before spouting off with our wisdom. My God, if you had 15" drop across a room, get the heck out of the house, it's a goner! My old kitchen had a slope of about 1/2" across 15". It was livable, but when water was spilled, you know where it all went! This section of the house was moved from its original site and there was a high corner on the foundation. Fix it with new joist and flooring. Had to do some creative ceiling work too to get the cabinets to fit. Just the joys of trying to make an old piece of #### work like new.

  9. #9
    Moderator & Master Plumber hj's Avatar
    Join Date
    Aug 2004
    Location
    Cave Creek, Arizona
    Posts
    25,651

    Default

    YOu CANNOT just "jack" the center of a tree story building up to level it. You have to do it in very TINY increments over several months to give the structure time to adjust to each adjustment.
    Licensed residential and commercial plumber

  10. #10
    DIY scratch-pad engineer leejosepho's Avatar
    Join Date
    Nov 2006
    Location
    200 miles south of Little Rock
    Posts
    2,474

    Default

    Quote Originally Posted by hj View Post
    YOu CANNOT just "jack" the center of a tree story building up to level it. You have to do it in very TINY increments over several months to give the structure time to adjust to each adjustment.
    Kind of like going to the chiropractor?!
    "Great minds discuss ideas, average minds discuss events and small minds discuss people." --Eleanor Roosevelt

  11. #11
    DIY Member pronouncedeyen's Avatar
    Join Date
    Sep 2009
    Location
    Baltimore, MD
    Posts
    46

    Default

    OK, more info guys. Thanks for all the discussion about house leveling. The house is 30' deep and has 2 main beams running across the basement from one end to the other. Both of those beams have center support footers that have sunk about 1.5". The settling probably happened 100 years ago and hasn't changed since we moved in 8 years ago. At least I don't think it has! The beam didn't settle linearly, that is, the settling is most pronounced closest to the brick. It drops 1" in the first 5 feet and then another 1/2" in the next 10 feet to the center support.

    Jacking up the house is a non-starter because the kitchen was built on the slanted floor. And I'm definitely not redoing the whole kitchen to accommodate a toilet upstairs!

    I remeasured and the 3/4" drop is across the alcove that the toilet sits in which is 34" wide. The drop across the toilet base is more like 3/8". Given that is there anything I can use to fill a whole that big? Do they sell something thicker than caulk?

  12. #12
    Test, Don't Guess! cacher_chick's Avatar
    Join Date
    Jan 2008
    Location
    Land of Cheese
    Posts
    3,147

    Default

    I would make a level form in the shape of the base of the toilet and pour a new base using cement, terrazzo, or epoxy resin.

  13. #13
    DIY scratch-pad engineer leejosepho's Avatar
    Join Date
    Nov 2006
    Location
    200 miles south of Little Rock
    Posts
    2,474

    Default

    How deep is that alcove? I think I would be inclined to use something like a super-tough, "self-leveling" (still has to be troweled) thinset type of filler material a flooring company once sold me for making a wheelchair ramp where a bedroom floor was somehow about an inch above a bathroom floor even though the two floors met just fine at their corner of the hallway. I would cover the entire width of the alcove to make it level while feathering the area in front of the toilet on out to nothing at an angle across its width and into the room to ultimately make the entire thing "disappear" after new flooring has been applied.
    Last edited by leejosepho; 07-24-2013 at 09:58 AM.
    "Great minds discuss ideas, average minds discuss events and small minds discuss people." --Eleanor Roosevelt

  14. #14
    DIY Member pronouncedeyen's Avatar
    Join Date
    Sep 2009
    Location
    Baltimore, MD
    Posts
    46

    Default

    I like the idea of pouring a base in the same shape as the toilet base. That way it will sit level and would be hardly noticeable! Would mortar be strong enough? I think it might be hard to pour concrete that's 1/2" on one side but almost 0 on the other.

  15. #15
    Test, Don't Guess! cacher_chick's Avatar
    Join Date
    Jan 2008
    Location
    Land of Cheese
    Posts
    3,147

    Default

    Quote Originally Posted by pronouncedeyen View Post
    I like the idea of pouring a base in the same shape as the toilet base. That way it will sit level and would be hardly noticeable! Would mortar be strong enough? I think it might be hard to pour concrete that's 1/2" on one side but almost 0 on the other.
    You could use self-leveling compound to pour a base that thin. There is the possibility that it would crack, but if you are pouring it in place it should be pretty solid. I don't know what you are dealing with, but I think it would be better to pour the entire bathroom floor.

Similar Threads

  1. HELP: Uneven AS toilet bowl after install
    By axelf911 in forum Toilet Forum discussions
    Replies: 8
    Last Post: 05-05-2012, 02:20 PM
  2. Uneven basement floor, how to install shower?
    By Bosun in forum Shower & bathtub Forum & Blog
    Replies: 2
    Last Post: 09-11-2007, 03:08 PM
  3. Shims/uneven floor causing leak?
    By suez in forum Toilet Forum discussions
    Replies: 2
    Last Post: 11-30-2005, 06:25 PM
  4. Water dumping on floor - Uneven Tub?
    By Heathers in forum Shower & bathtub Forum & Blog
    Replies: 7
    Last Post: 05-14-2005, 03:19 PM
  5. Need advice on installing a bathtub on uneven floor
    By Cindy in forum Shower & bathtub Forum & Blog
    Replies: 4
    Last Post: 10-16-2004, 03:41 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •