Originally Posted by
LLigetfa
I'm not a well driller so cannot answer that but will take a stab at it. I don't think they intended it to be a mud well. They originally welded on a drive shoe probably with the intent on setting it into the bedrock in anticipation of it being a rock well. I think they drove down the casing as they went, not knowing the formation until after they passed it. I'm guessing they didn't want to pull up all the casing to add screen to the last 5 feet of it and thought the glacial till would be stable enough to be the screen.
They did not actually develop the well and only pumped it at 5 GPM to satisfy the minimum requirement. After I built the house I put in my 10 GPM pump, it sucked in the mud and I had to get the driller back to flush it out and set the gravel pack. It filled back in with mud again and I augered it out by hand and developed the well myself after the driller did a bunch of no-shows.