    I'm a DIYer finishing my basement. The floor is concrete, which I will tile. The builder left a rough-in for a tub and toilet. I've framed the area for the tub and plan to install a one piece acrylic tub/shower combo, Delta model 226032A. I get how to do all the plumbing for the supply/mixer/showerhead. I understand how to connect the drain assembly to the tub. I'm lost on how to attach the assembly to the rough-in stub that the builder left. I assume that I put in a trap, with the opening lined up with the straight pipe coming off the drain assembly, so that the drain slides into the trap. But how am I supposed to attach those pipes? The trap is down inside the concrete, and it will all be covered by the tub once I put the thing together. I'm confused.

  2. #2
    Retired Defense Industry Engineer jadnashua's Avatar
    Join Date
    Sep 2004
    Location
    New England
    Posts
    21,376

    Default

    A plumber would measure carefully, apply cement, set the tub in place and be done. Practice helps immensely and once you add the cement, you only get one chance. If you don't have an access panel on that wet end, that's about the only way to do it.
    Jim DeBruycker
    Important note - I'm not a pro
    Retired Defense Industry Engineer; Schluter 2.5-day Workshop Completed 2013, 2014

  3. #3
    Moderator & Master Plumber hj's Avatar
    Join Date
    Aug 2004
    Location
    Cave Creek, Arizona
    Posts
    25,605

    Default

    A plumber would prefit the drain assembly to the tub then remove it. He would measure carefully and attach the drain to the drain pipe, set the tub in place OVER it, then connect the drain assembly to the tub.
    Licensed residential and commercial plumber

  4. #4
    DIY Junior Member Al Pine's Avatar
    Join Date
    Mar 2012
    Location
    Maryland
    Posts
    3

    Default

    Thank you both for your replies. They are very different approaches. I think the one that makes the most sense is to set the drain assembly and then install the tub onto it. I'd like to see if anyone else has any input. Also, for the drain stub that the builder left in the rough-in box: it's in gravel inside a ~8"x10" cut out in the concrete. I haven't dug into it yet (the house is several hours away & I only get there a couple of weekends a month). There is a PVC pipe running horizontally coming from the wall with about 4" showing out of the gravel. Is it typical for this to have a trap already in the run, or do I need to add one? What about venting, is the drain usually on the main vent stack?

    Thanks.

  5. #5
    Moderator & Master Plumber hj's Avatar
    Join Date
    Aug 2004
    Location
    Cave Creek, Arizona
    Posts
    25,605

    Default

    It would be unlikely to have a trap if the pipe is horizontal, and the vent should be somewhere before it gets that far.
    Licensed residential and commercial plumber

  6. #6
    Forum Admin, Expert Plumber Terry's Avatar
    Join Date
    Aug 2004
    Location
    Bothell, Washington
    Posts
    14,191
    Blog Entries
    1

    Default

    Most plumbers box out and leave the trap installation for the installing plumber after the walls have been framed in.
    If a trap had been installed at rough-in, which it seems this one wasn't, it would almost never be spotted correctly for the tub anyway. Too much can happen between the concrete pour and the framing of the walls.

    HJ has it right; Install the tub waste and overflow to the tub first, remove it from the tub and install the drain to the p-trap in the floor. Then you can put the tub in and attach the fittings through the tub after it's in place. It's much easier to get the tub drain right, with the tub in the open and accessible.

  7. #7
    DIY Junior Member Al Pine's Avatar
    Join Date
    Mar 2012
    Location
    Maryland
    Posts
    3

    Default

    Thank you HJ and Terry. That makes sense. But I have a feeling that about halfway through this I'll have a new appreciation for you guys that do this for a living, and an expanded four letter word vocabulary.

Similar Threads

  1. Shower pan installation
    By pdwilly in forum Shower & bathtub Forum & Blog
    Replies: 6
    Last Post: 11-01-2009, 01:13 AM
  2. Shower installation
    By slanderman in forum Plumbing Forum, Professional & DIY Advice, Tips & Tricks
    Replies: 13
    Last Post: 08-11-2007, 10:55 PM
  3. Shower arm installation
    By dogs01 in forum Shower & bathtub Forum & Blog
    Replies: 2
    Last Post: 03-27-2007, 03:00 PM
  4. Shower Pan Installation
    By elgato in forum Shower & bathtub Forum & Blog
    Replies: 2
    Last Post: 01-27-2007, 10:46 PM
  5. Tub & Shower Installation
    By LarryD in forum Plumbing Forum, Professional & DIY Advice, Tips & Tricks
    Replies: 2
    Last Post: 08-21-2005, 01:49 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •