Daler
Member
My 'big picture' involves making the ensuite bath a tad larger by stealing room from the adjacent main bath. In the process we will also enlarge a bedroom closet.
The first project will be taking care of the main bath, while maintaining use of the existing ensuite shower, etc.
The old monster jacuzzi tub has been torn out and a new soaker tub is to be installed about 5' further away against an exterior wall. The toilet is moving 18" further into the room (along its same joist) to make way for the tub. What I want to know is the best way of tapping into the existing plumbing stack (where current shower is and the previous jacuzzi used to be plumbed into) -- see .jpg of existing crawlspace plumbing.
To maintain the existing shower (but to prepare for its move in the next project phase), what I propose to do is to cut everything back from just below the current shower wye and down to the 2" lateral going to the main sewer line. Then connect the new tub drain (Canadian Code seems to ok up to 8' trap arm for a 2" drain) to the remaining lateral using a new wye, and another new wye with a stub out (capped) for the future shower drain (about 4' away from the vent stack). As you may see these new connections will now be down about 2.5 feet from the original connections up near the floor joists. I would then finish off the 2" lateral with a new cleanout at the end.
Later, in the next phase I plan to go back and cut off the old shower drain trap at its old wye and just cap it.
So in essence, the whole stack from the new lateral wye's on up would just be an extension of the existing vent.
Do you think this is a workable plan, or perhaps suggest better alternatives?
The first project will be taking care of the main bath, while maintaining use of the existing ensuite shower, etc.
The old monster jacuzzi tub has been torn out and a new soaker tub is to be installed about 5' further away against an exterior wall. The toilet is moving 18" further into the room (along its same joist) to make way for the tub. What I want to know is the best way of tapping into the existing plumbing stack (where current shower is and the previous jacuzzi used to be plumbed into) -- see .jpg of existing crawlspace plumbing.
To maintain the existing shower (but to prepare for its move in the next project phase), what I propose to do is to cut everything back from just below the current shower wye and down to the 2" lateral going to the main sewer line. Then connect the new tub drain (Canadian Code seems to ok up to 8' trap arm for a 2" drain) to the remaining lateral using a new wye, and another new wye with a stub out (capped) for the future shower drain (about 4' away from the vent stack). As you may see these new connections will now be down about 2.5 feet from the original connections up near the floor joists. I would then finish off the 2" lateral with a new cleanout at the end.
Later, in the next phase I plan to go back and cut off the old shower drain trap at its old wye and just cap it.
So in essence, the whole stack from the new lateral wye's on up would just be an extension of the existing vent.
Do you think this is a workable plan, or perhaps suggest better alternatives?