Hope you guys could help me out. I’m trying to help out a friend with setting up his dwv setup in his bathroom and was hoping you could point me in the right direction. Here are a couple of pics that I took. Which one would be the correct setup? Please, if we’re totally off, let us know which way is correct
None of those would work if you are using the UPC code.
Thanks for your reply.
Could someone please explain the best way to set this up. Any suggestion is greatly appreciated.
Thanks.
There could be several "correct" ways to do it, you just picked two that were not. One of the biggest corrections is that you cannot have the toilet flowing past the shower connection, unless you have a vent between the shower trap and the 3" connection. Other items, such as how you vent the toilet would depend on how lenient the inspector was that day, but most would not allow the vent to continue horizontally after the toilet opening.
What's up everyone.....
Now that the hurricane is going and have power we could now finish this project. Could you please take a look and tell us what you think. Please.
Thanks....
you haven't addressed post #4. vent the shower and roll the toilet vent.
Could you guys tell me which would be the correct way to set this up.....
Thanks in advance.....
Hope everyone had a great Christmas.
I think I got it this time.
How about this setup.
We are planning on moving the 3' main from the left side to the right side.
I hope the picture makes sense.
Thanks.....
Last edited by 01sesedan; 12-30-2005 at 07:06 PM.
New drawing, it's a little rough but I hope it makes .
Is the circle where the water closet will go? At the end of your 2" line your lavatory with a a branch off to pick up the shower?
That's how I see it and if those answers are yes then your system will work.
Matt
Semi-professional plumbing designer
Enjoying life in SW Florida
I cannot follow the stick drawing but if that picture is followed the way you have the fittings laid out, in about 1 to 3 years the vents are going to seal up since you are flat venting under 42". Not acceptable. Groundwork when it comes to plumbing is crucial, otherwise the alternative is years of drain problems........
Read what the end of this sentence means.
Hope this drawing makes more sense.
Thank for your replies..
Happy New Year..
looks right. imo. make sure to roll your your vents upward. p trap for shower must be glue type. when connecting vents pitch upward and increase pipe size thru roof.
Here's a view of the vents going up the wall.
Hope this one makes sense.
So, what do you guys think?
Last edited by 01sesedan; 01-09-2006 at 01:32 PM.