gt2nome
New Member
I'm building a house in VA and wanted to rough-in plumbing for a future basement bathroom. My plumbing knowledge is 1/4" per foot, it all flows downhill and vent pipes are a royal pain to figure out.
My questions are:
1) I have placed a 6" sleeve under the footer before it was poured, so I assume the main stack should go about 16-24 inches away from the wall, directly in front of sleeve (upstairs baths and kit. directly above)?
2) To tie the toilet drain (4") into main stack do I use a long sweep T-Y, or a regular T?
3) The toilet drain is only 3'6" away from main stack. Shower and sink are on either side of toilet. Should I relocate to obtain more room to place Y fittings for shower and sink? Or is there such a thing as double Y (4"x4"x2"x2")?
This is what I have sketched out so far:
Thanks,
My questions are:
1) I have placed a 6" sleeve under the footer before it was poured, so I assume the main stack should go about 16-24 inches away from the wall, directly in front of sleeve (upstairs baths and kit. directly above)?
2) To tie the toilet drain (4") into main stack do I use a long sweep T-Y, or a regular T?
3) The toilet drain is only 3'6" away from main stack. Shower and sink are on either side of toilet. Should I relocate to obtain more room to place Y fittings for shower and sink? Or is there such a thing as double Y (4"x4"x2"x2")?
This is what I have sketched out so far:
Thanks,