Hello,

I am starting a basement remodel and am in the stages of planning the plumbing for a laundry room/bathroom. I am sure I will have many questions and this forum has been very helpful so far. Attached is a drawing of what I would like to do and I am not sure if there are any issues with it but basically I would like to:

Run a 2" laundry drain 8 feet or so to the 3" or 4" line that exits my home. With everything that I have read it seems that I will need to vent this line. Since I am in the basement I was thinking that I would just wye a 1.5" vent to the 1.5" drain for my first floor shower that is about 4 or 5 feet from a stack. Will there be any issues with this? Thanks.

bengal21
 

Attachments

  • DeletFile.pdf
    8.5 KB · Views: 217

bengal21

New Member
Messages
21
Reaction score
0
Points
0
Location
Des Moines
If I am not allowed to vent the laundry line in the basement through the shower drain line could I tie the 1.5" vent line into the stack above the toilet but below the sink? Or does the vent have to be above the highest fixture on the stack? I am hoping that it only has to be above the toilet drain line :eek:
 

JohnjH2o1

Plumbing Contractor for 49 years
Messages
1,188
Reaction score
13
Points
38
Location
Florida
The vent for the laundry must go out the roof or tie in 6" above the flood rim of the highest fixture on the stack.

John
 

Shacko

Master Plumber-Gas Fitter
Messages
559
Reaction score
1
Points
0
Location
Rosedale, Md
What part of your sketch is under concrete? if that vent is under concrete it should be 2in., the pipe to the shower should also be 2in. Like the other post said your vent will have to tie in above the FLOOD LEVEL RIM of the highest fixture, that usually comes out to 42in above the floor. Any fixture below another fixture has to have a vent. Work on your design some more. :confused:
 

Terry

The Plumbing Wizard
Staff member
Messages
29,942
Reaction score
3,459
Points
113
Location
Bothell, Washington
Website
terrylove.com
The vents need to tie in above the flood level of the fixtures being connected.
That would be 6" above the sink upstairs.
Not on the shower trap arm.

dwv_b2.jpg
 
Top
Hey, wait a minute.

This is awkward, but...

It looks like you're using an ad blocker. We get it, but (1) terrylove.com can't live without ads, and (2) ad blockers can cause issues with videos and comments. If you'd like to support the site, please allow ads.

If any particular ad is your REASON for blocking ads, please let us know. We might be able to do something about it. Thanks.
I've Disabled AdBlock    No Thanks