glenmb
New Member
Hi Everyone
My inspector has flagged my shower design in my permit application - he says based on his DFU claculation I need 2 shower drains
Design Plan
4x5 Shower - one 2 inch drain
Moen 3/4" thermostatic valve feeding 4 volume contols for:
Overhead shower - 2.5GPM
Fixed Shower - 2.5GPM
Slide Bar - 2.5GPM
3 Body Sprays - 3@1.8GPM ea - 5.4GPM total
The inspector is a good guy but his DFU explanation was a little unlclear - I was hoping someone could look at the above and see if I have any standing to debate - or at least clarifu DFU limits etc
Also - if I do have to add another drain in the shower - I assume that has to be a seperate trap as well with a wye tying into the drain line similar to the existing drain setup?
Many thx in adavance for any guidance - glenn
My inspector has flagged my shower design in my permit application - he says based on his DFU claculation I need 2 shower drains
Design Plan
4x5 Shower - one 2 inch drain
Moen 3/4" thermostatic valve feeding 4 volume contols for:
Overhead shower - 2.5GPM
Fixed Shower - 2.5GPM
Slide Bar - 2.5GPM
3 Body Sprays - 3@1.8GPM ea - 5.4GPM total
The inspector is a good guy but his DFU explanation was a little unlclear - I was hoping someone could look at the above and see if I have any standing to debate - or at least clarifu DFU limits etc
Also - if I do have to add another drain in the shower - I assume that has to be a seperate trap as well with a wye tying into the drain line similar to the existing drain setup?
Many thx in adavance for any guidance - glenn