JThiessen
New Member
Hi everyone. I've been a long time "browser" of these forums, and have gained much knowledge from the members here.
I finally ran into a situation wher I now need to ask my own question (I searched, but found no threads that addressed this.)
I'm remodeling my master bathroom, and one item is a new soaking tub to replace the old standard tub. I have the hot and cold stub ups sticking through the floor, the rough in valves are temporarily installed in the tub (I mounted them to the tub flange). I have not yet completed the deck around the tub, nor is the tub "set" in yet.
The engineer in me tends to overthink things, so now I've found my self scratching my head on how exactly to connect the supply lines to the valves.
1) Do I complete the tub installation, and direct connect the lines to the valves? This would be the most sound installation, but it would also be a little difficult to do the final soldering joints.
2) Do I install shut off valves in line? If so, under the deck, below the floor (piping is in the garage ceiling). I'm not a fan of this one, since valves will likely develop a leak somewhere down the line, probably not for me, but maybe with a future owner.
3) If neither of the above, is it common to use screw on supply hoses similar to a sink installation? Or some other threaded style joint? I'm not inclined to use this method either due to the propensity for leaking.
The reason I guess I am overthinking this is that sometime down the road, someone else may have to work on this, and I'd like to make it as robust as I can. I do have limited access from below that would make a threaded connection possible to access - but still not as easy as I'd like. And yes, I will be making the front panel on the deck removable in some fashion.
Thanks in advance for your advice.
I finally ran into a situation wher I now need to ask my own question (I searched, but found no threads that addressed this.)
I'm remodeling my master bathroom, and one item is a new soaking tub to replace the old standard tub. I have the hot and cold stub ups sticking through the floor, the rough in valves are temporarily installed in the tub (I mounted them to the tub flange). I have not yet completed the deck around the tub, nor is the tub "set" in yet.
The engineer in me tends to overthink things, so now I've found my self scratching my head on how exactly to connect the supply lines to the valves.
1) Do I complete the tub installation, and direct connect the lines to the valves? This would be the most sound installation, but it would also be a little difficult to do the final soldering joints.
2) Do I install shut off valves in line? If so, under the deck, below the floor (piping is in the garage ceiling). I'm not a fan of this one, since valves will likely develop a leak somewhere down the line, probably not for me, but maybe with a future owner.
3) If neither of the above, is it common to use screw on supply hoses similar to a sink installation? Or some other threaded style joint? I'm not inclined to use this method either due to the propensity for leaking.
The reason I guess I am overthinking this is that sometime down the road, someone else may have to work on this, and I'd like to make it as robust as I can. I do have limited access from below that would make a threaded connection possible to access - but still not as easy as I'd like. And yes, I will be making the front panel on the deck removable in some fashion.
Thanks in advance for your advice.