cicerored
New Member
I am about 1/2 way there with the removal of the slab. But I think you can get a good idea of what I want to do.
I have a sink, toilet roughed in, in my basement. I am adding a shower rough in, because I am going to finish the basement. The sink has a 1.5" vent that goes out the ceiling and connects to the main stack in the attic.
I am going to have the bathroom fixtures lined up in the following order: sink, toilet, shower
In the picture you can see where the sink and toilet hook into the main waste line.
I want to use a 4x2 Wye to connect to the 4" line, then a 2x2 wye, then 2x2 pipe - one line to the p-trap/drain, one vent over to the wall and up to the ceiling level where I will run it over to the sink vent (the shower trap will be about 7 feet away from the sink vent).
Will this work?
Thanks
I have a sink, toilet roughed in, in my basement. I am adding a shower rough in, because I am going to finish the basement. The sink has a 1.5" vent that goes out the ceiling and connects to the main stack in the attic.
I am going to have the bathroom fixtures lined up in the following order: sink, toilet, shower
In the picture you can see where the sink and toilet hook into the main waste line.
I want to use a 4x2 Wye to connect to the 4" line, then a 2x2 wye, then 2x2 pipe - one line to the p-trap/drain, one vent over to the wall and up to the ceiling level where I will run it over to the sink vent (the shower trap will be about 7 feet away from the sink vent).
Will this work?
Thanks