  1. #1

    Default Schedule 40 PVC vs. Schedule 40 Foam Core

    My wife and I are building a house. The builder(gen'l contractor) was instructed to use Schedule 40 PVC and now we see there is Schedule 40 Foam Core in the house (including the exterior waste lines). The walls are not yet closed. The builder & plumber said that Foam Core is they typical product of choice and that we shouldn't worry about it. I called Charotte yesterday and asked the rep. if he was building his home what would he use and the answer was Schedule 40 PVC.

    What do you think? Are the two pipes of equal quality? Are we being to picky? This is an expensive custom house that, until up till now, has been built beautifully (both structurally and visually).

    Thank you in advance.

  2. #2
    Moderator & Master Plumber hj's Avatar
    Join Date
    Aug 2004
    Location
    Cave Creek, Arizona
    Posts
    23,717

    Default pipe

    Schedule 40 is a measurement, not the pipe's quality. All sch.40 pipe will have the same i.d. and o.d. which means the wall thickness will be the same. That has nothing to do with HOW the pipe is made, i.e. solid core or foam core. We do not use PVC drain lines here, but where it is used, foam core seems to be the material of choice for drain lines. But it is not a "pressure" material so it is not used for supply water lines. If it were a problem for you, your specification should have called for scheduler 40 pressure rated piping.
    Last edited by hj; 04-09-2008 at 05:57 AM.

  3. #3
    Retired Defense Industry Engineer jadnashua's Avatar
    Join Date
    Sep 2004
    Location
    New England
    Posts
    19,402

    Default

    I'd call the manufacturer for thoughts. My gut feel is that the foam core stuff is more susceptable to getting crushed underground under adverse conditions - it isn't as strong (but might be more flexible which could help - I don't know, this is a guess). Those shouldn't happen, but could. Inside the house, I wouldn't have big problems with either, it is only outside I'd have to give it a second thought.
    Jim DeBruycker
    Important note - I'm not a pro
    Retired Defense Industry Engineer; Schluter 2.5-day Workshop Completed 2013

  4. #4

    Default

    Not sure but I hear it is against code in WI to use foam core pvc in the dwv lines....

  5. #5

    Default

    Gentleman,

    Thanks for the help. I called the manufacturer again today and the tech was extremely confident that the foam core would work fine. I also spoke to the local inspector who was also sure it would work properly.

    My frustration is that the foam core was not specified but installed. Do I win the battle (by having them spend the time and money replacing it) and possible lose the war when the project grinds to a halt. GC omits to the mistake but has not really come up with a solution.

    Dazed and Confused in DC who now knows more about PVC pipe than I ever thought I would.

    Ross

  6. #6
    DIY Member rombo's Avatar
    Join Date
    Mar 2008
    Location
    Ontario
    Posts
    62

    Default

    i wouldn't worry about

  7. #7
    DIY scratch-pad engineer leejosepho's Avatar
    Join Date
    Nov 2006
    Location
    200 miles south of Little Rock
    Posts
    2,345

    Default

    Quote Originally Posted by rombo View Post
    i wouldn't worry about
    Same here. I first saw it when the regular stuff was scarce right after Katrina, and I have used it both inside and outside without problems.

  8. #8

    Default

    Here's how I see it.You could request the materials price be reduced by the difference between the pipe prices.But if you did that,you would probably have to absorb the recent large increases in PVC cost.So it would basically wash out anyway.
    I say no harm,no foul,let it slide.

  9. #9
    Sound and Light Suppervisor for a School District tjbaudio's Avatar
    Join Date
    Dec 2005
    Location
    Wisconsin
    Posts
    161

    Default

    As long as there are no long unsupported lines the your fine. This would hold true for any material. I have the foam core stuff and it is not a problem. If the building inspector is happy let it go. It will not affect the value of the home any way.
    tjbaudio
    I have a mild form of Dyslexia that affects my ability to spell. I do use spell checking to help but it does not always work. My form of Dyslexia does not affect my reading. Dyslexics of the world untie!

    www.incertclevername.com

  10. #10
    DIY Junior Member fozzy12's Avatar
    Join Date
    Jan 2008
    Location
    North of Detroit, MI
    Posts
    27

    Default Foam core PVC

    Let it slide, it isn't affecting anything. The GC admits it was a mistake, he knows you're paying attention. He will probably be a little more careful in the future. No sense starting a needless war if you like what he's done so far.

    Eric

  11. #11
    I&C Engineer (mostly WWTP) Lakee911's Avatar
    Join Date
    Aug 2005
    Location
    Columbus, OH
    Posts
    1,329

    Default

    Let it slide inside, but check the city code to see if you can use it outside underground.



    Jason

  12. #12
    Master Plumber Dunbar Plumbing's Avatar
    Join Date
    Apr 2005
    Location
    Northern Kentucky/Greater Cincinnati Area
    Posts
    2,944

    Default

    The only performance issues I've seen with the product is how you have to lip the ends of the pipe with glue and cleaner when preparing the solvent weld joining method to prevent an air test failure.

    Meaning, if you don't consider this practice you'll have problems with getting air tests to properly hold for inspections, due to the fact that air can travel through the piping walls.

    I guarantee your plumbers did this to protect this situation from happening, otherwise they know the fix. Tear it out!

    When foam core came out eons ago, we were told to make this a common practice in order to get air tests to hold 5 pounds of air.
    Read what the end of this sentence means.

  13. #13
    DIY Senior Member rdtompki's Avatar
    Join Date
    Dec 2005
    Location
    Iowa
    Posts
    115

    Default

    I'm a bit confused about the part of the original question that talks about the PVC being inside the "walls" or is the original question only referring to drain and waste in the walls vs. potable water?

    Rick

  14. #14
    Plumber BAPlumber's Avatar
    Join Date
    Jul 2007
    Location
    Vashon, Washington
    Posts
    227

    Default

    Quote Originally Posted by ROSSBYINGTON View Post
    My wife and I are building a house. The builder(gen'l contractor) was instructed to use Schedule 40 PVC and now we see there is Schedule 40 Foam Core in the house (including the exterior waste lines). The walls are not yet closed. The builder & plumber said that Foam Core is they typical product of choice and that we shouldn't worry about it. I called Charotte yesterday and asked the rep. if he was building his home what would he use and the answer was Schedule 40 PVC.
    It sounds like the GC did what he was instructed. He used Sch. 40 PVC. If he was instructed to use Sch. 40 Solid Core PVC and didn't, then there may me a problem. The pipe will work fine, it just isn't what was contracted for.