    When our house was built 3 years ago, we had the basement roughed in for a bathroom. I recently started finishing it and never really looked at the plumbing until now. I have a few questions I hope you guys can answer for me:

    1. The large pipe to the left runs into the ceiling. I assume it's a vent? I also assume the capped pipe to the left of the toilet flange is the drain for the sink? What would the pipe to the right of the toilet flange be (with the p-trap)?

    2. The toilet flange is the standard 12" from the wall you see in the picture, however the pipes coming up are on the inside of the wall. How do I frame these pipes in as well as keep enough distance to install a toilet?

    3. The grey shower drain box only extends 4 3/4 inches from the wall in the picture. Does this seem a little tight?

    Thanks in advance for any help you guys can provide.



    Terry's input here
    The 2" pipe on the left, that goes through ceiling is most likely the lav drain, and the vent for the entire bathroom set.
    It would need a 2" x 1-1/2" Santee cut in for the lav.
    Above that, at 42", you would cut in a 2" santee, go to the right, and pick up the toilet vent, and then over to the tub vent.
    You must keep all the vents.

    Last edited by Terry; 02-14-2008 at 08:29 AM.

  2. #2
    Plumber krow's Avatar
    Join Date
    Feb 2008
    Location
    Ontario, Canada
    Posts
    906

    Default

    1) The pipe to the left looks like a vent. The pipe to the left of the flange could be the WC vent or wet vent (Depending of the diametre of that pipe). The pipe on the right might be a wet vent for the shower/bathtub rough-in. Its hard to tell without knowing your basement layout.

    In my area, we have to connect all the vents at the rough-in stage with the appropriate T's, whether you finish the basement or not

    2) If you don't want to dig into the cement and extend those 2 pipes straight into the wall, you could cut the pipes at about 3/4" off the floor and offset them with 2 - 45's into the wall

    3) The drain box seems to be roughed in for a bathtub. If you want a shower, you may end up chopping some cement to relocate your new shower drain.


    I hope I help from what I could see

  3. #3

    Default

    1. The diameter of the pipes to the left and right of the toilet flange are 1 1/2". Can these just be vented into an open cavity?

    2. If I dont want to cut the concrete, will this mean that I'll be able to see the piping at the bottom of the wall before I turn them inside the wall?

    3. By shower I meant tub/shower. One of those 1 piece fiberglass deals. How far from the wall to those normally drain?

  4. #4
    Licensed Plumbing & Gas Contractor.
    Join Date
    Feb 2008
    Location
    Oklahoma City
    Posts
    14

    Default

    The rough-in is wrong.Never inspected I'm sure.Correcting it may not be possible with-out moving the walls or busting up the floors.We would need measurements to know for sure either way.

  5. #5

    Default

    Wow. Nice to pay $1300 for the rough in to find out it's wrong. Probably why my builder filed for bankruptcy this year.

    Unfortunately, the wall existing is load bearing so I can't do much with it.

    As for measurements, not really much there. The existing pipes butt up against the wall in the picture and the toilet flange is 12"-c- from the same wall.

  6. #6
    In the Trades Gary Swart's Avatar
    Join Date
    Sep 2004
    Location
    Yakima WA
    Posts
    7,246

    Default

    Rough ins are offer done poorly, and unfortunately, since they almost always are in a basement and therefore cast in concrete, it becomes a major problem to fix. It would be my suggestion to call in a plumber to determine what needs to be done. There are some things that are difficult to impossible to determine without being on site.

  7. #7
    Licensed Plumbing & Gas Contractor.
    Join Date
    Feb 2008
    Location
    Oklahoma City
    Posts
    14

    Default

    Quote Originally Posted by kregas View Post
    Wow. Nice to pay $1300 for the rough in to find out it's wrong. Probably why my builder filed for bankruptcy this year.

    Unfortunately, the wall existing is load bearing so I can't do much with it.

    As for measurements, not really much there. The existing pipes butt up against the wall in the picture and the toilet flange is 12"-c- from the same wall.
    I'm sorry about that.It would be a one day,day-and a half job, to bust a little of the floor and make it work.You'll have to take the plumbing to the walls.It needs inspection.I would have installed a right-handed tub instead for access to the tub-box after the tub is set.Good-luck.

  8. #8
    Licensed Plumbing & Gas Contractor.
    Join Date
    Feb 2008
    Location
    Oklahoma City
    Posts
    14

    Default

    If I read wrong and it is a shower,center of your shower stall is the normal place for the drain.But it doesn't have to be in the center,it is just more practical.

  9. #9
    Licensed Plumbing & Gas Contractor.
    Join Date
    Feb 2008
    Location
    Oklahoma City
    Posts
    14

    Default

    And why is there a stand-pipe/indirect waste in your bathroom.Hope that's not supposed to be the lav.

  10. #10

    Default

    I'm not sure I understand your questions.

    I'm putting in a left hand 60" x 35" tub/shower. It "should" line up to the drain pit.

    Not sure what you mean by stand pipe/indirect waste

  11. #11
    Licensed Plumbing & Gas Contractor.
    Join Date
    Feb 2008
    Location
    Oklahoma City
    Posts
    14

    Default

    Got ya.Okay,that pipe next to the toilet flange is a indirect waste that can be used for a clothes washer or water softener [the one with the trap] and that is about the only residential application .The tub-box should have bein on the other side of the tub to the right in order to be worked on in the future,unless there is room to work that I can't see.Speaking of work ,gotta go.

  12. #12
    DIY Senior Member MG's Avatar
    Join Date
    Jun 2005
    Location
    Illinois - Near St. Louis
    Posts
    160

    Default

    I hope that flange is not glued in at the floor...because if you want to install tile you're going to have a fun time. Flanges should sit on top of the finished floor to make it easier to seat the toilet.
    Note: I am a DIY'er and not a professional. My posts here are observations / opinions and may or may not be in accordance with your local ordinances.

  13. #13

    Default

    No, that's the only thing that actually looks correct in the rough-in. Just a bad angle in the picture is all.

    Not trying to stir the pot, but who's to blame in all this? Plumber? Builder? Inspector?? There was a reply before that rough-in's are often done poorly. If this is common knowledge, how does it continue to happen?

  14. #14
    Licensed Plumbing & Gas Contractor.
    Join Date
    Feb 2008
    Location
    Oklahoma City
    Posts
    14

    Default

    Quote Originally Posted by kregas View Post
    No, that's the only thing that actually looks correct in the rough-in. Just a bad angle in the picture is all.

    Not trying to stir the pot, but who's to blame in all this? Plumber? Builder? Inspector?? There was a reply before that rough-in's are often done poorly. If this is common knowledge, how does it continue to happen?
    Someone overlooked something .Were there prints ?Who was responsible for overseeing the job?That's where you'd have to start.

  15. #15
    Plumber krow's Avatar
    Join Date
    Feb 2008
    Location
    Ontario, Canada
    Posts
    906

    Default

    Quote Originally Posted by kregas View Post
    Not trying to stir the pot, but who's to blame in all this? Plumber? Builder? Inspector??
    IMO, a plumber should have known better to place the flange at 12" rough when the pipes are sticking outside the wall.

    It should have been 12 3/4" from the edge of the pipe to the center of the flange. That way you could fir out the wall to hide pipes. The 3/4" is to allow for sheetrock and tiles(optional). Then you will be 12" from finished wall