Hids2000
New Member
I need some help with rough in. Attached are 2 pics of what I did.
There are two 14-2 providing power to 4 switches. I labeled each wire it may be hard to see the labels.
One of the 14-2 will provide power to 600watt track light switch and an outside 100watt light switch.
The other 14-2 will provide power to two switches each controlling a 50†ceiling fans.
The inspector came today and left in 10 secs. He said it is not ready, because the splices are not done.
I thought “rough in†is just having the correct wire, making sure the wire is stapled to the posts correctly? When I asked him what it means to have the “all the splices done†he said go call an electrician.
Only thing I can think of that he wants me to remove the rubber sheathing from the NM wires, and splice and wire nut all the grounds and natural together. But since I can’t install any of the switches yet. Do I just leave the black wire alone?
Any help and suggestion is much appreciated.
There are two 14-2 providing power to 4 switches. I labeled each wire it may be hard to see the labels.
One of the 14-2 will provide power to 600watt track light switch and an outside 100watt light switch.
The other 14-2 will provide power to two switches each controlling a 50†ceiling fans.
The inspector came today and left in 10 secs. He said it is not ready, because the splices are not done.
I thought “rough in†is just having the correct wire, making sure the wire is stapled to the posts correctly? When I asked him what it means to have the “all the splices done†he said go call an electrician.
Only thing I can think of that he wants me to remove the rubber sheathing from the NM wires, and splice and wire nut all the grounds and natural together. But since I can’t install any of the switches yet. Do I just leave the black wire alone?
Any help and suggestion is much appreciated.