rlmaier
New Member
To all,
I’m planning on building a detached garage/shop in the near future. I would like to rough-in the drain system for a sink and a toilet prior to the contractor pouring the concrete slabs. My building site has approximately 7 foot of slope running from one end of the building to the other (52†total). To lessen the amount of excavation and the amount of fill, I’ve decided to pour one slab 40 inches higher then the other. In other words, the garage portion of the building (the right side) will be 40 inches higher than the shop portion of the building (the left side). I’ve enclosed a picture of the layout. If it’s not obvious, the slope of the land is from right to left.
I need some help in designing the drain system given that my septic system will be approximately 44 feet from these fixtures. The toilet will sit on the upper slab and the sink on the lower slab. The elevation difference between the toilet and the septic system is almost 7 feet.
My initial idea is to plumb the sink drain through the block wall (to the right) and tie into the drain for the toilet. I will then drop vertical to a point where I can begin my slope under the lower shop slab to the septic system. I realize that all the books say that the slope of the drain must be at least ¼ inch of drop for every horizontal foot. Given that formula, my total drop is 11 inches. Due to the distance I have to go to my septic system (~44 feet), is there any advantage to increasing the slope of the drain or does that cause other problems? Is there an advantage of using a 4†main drain versus a 3�
Also, since my two fixtures are within 4 feet of each other, will one 2 inch vent be sufficient? If not, I can vent the sink at the block wall and vent the toilet just above where it connects to the main.
Sorry about all the questions but I’m trying not to make any big mistakes. Thanks in advance for any advice I can get.
Regards,
Reid
I’m planning on building a detached garage/shop in the near future. I would like to rough-in the drain system for a sink and a toilet prior to the contractor pouring the concrete slabs. My building site has approximately 7 foot of slope running from one end of the building to the other (52†total). To lessen the amount of excavation and the amount of fill, I’ve decided to pour one slab 40 inches higher then the other. In other words, the garage portion of the building (the right side) will be 40 inches higher than the shop portion of the building (the left side). I’ve enclosed a picture of the layout. If it’s not obvious, the slope of the land is from right to left.
I need some help in designing the drain system given that my septic system will be approximately 44 feet from these fixtures. The toilet will sit on the upper slab and the sink on the lower slab. The elevation difference between the toilet and the septic system is almost 7 feet.
My initial idea is to plumb the sink drain through the block wall (to the right) and tie into the drain for the toilet. I will then drop vertical to a point where I can begin my slope under the lower shop slab to the septic system. I realize that all the books say that the slope of the drain must be at least ¼ inch of drop for every horizontal foot. Given that formula, my total drop is 11 inches. Due to the distance I have to go to my septic system (~44 feet), is there any advantage to increasing the slope of the drain or does that cause other problems? Is there an advantage of using a 4†main drain versus a 3�
Also, since my two fixtures are within 4 feet of each other, will one 2 inch vent be sufficient? If not, I can vent the sink at the block wall and vent the toilet just above where it connects to the main.
Sorry about all the questions but I’m trying not to make any big mistakes. Thanks in advance for any advice I can get.
Regards,
Reid