Sewer line embedded or below slab? (1950's house - St. Paul, MN)

Bucky

New Member
Messages
15
Reaction score
0
Points
1
Location
Minnesota
Just curious what the typical building protocol was in the 1950's. I'm remodeling my basement and need to set some tapcons into the floor and I obviously don't want to hit the sewer line. Is it likely embedded in the slab or running underneath it? Or is it a crap shoot?
 
The sewer lines should at least be under the concrete which is 4" thick. Unless your using tap cons longer then 4" it shouldn't be a problem.

John
 
IF the sewer were imbedded in the concrete, it would be obvious, because there would be a crack in the concrete right above it following the sewer's route.
 
Back