gatorheel
New Member
Hi all,
I've been lurking for months as we planned our renovation, and the framers have our addition to the point where I need to get my rough-ins done. I've worked up the following from what I've read here and my reading of the code. I'd really appreciate any feedback-- it's easy for a beginner like me to get the wrong fitting...
Some background. The house is a 1910 Florida Craftsman that's long suffered at the hand of the unpermitted DIYer. I'm cleaning up issues as fast as I can, but in the meantime we're adding a garage and laundry room. In the laundry, we'll have a sink and washer, so I'm planning to size drains @ 2" for the 4 DFUs. In both sketches below the joists run from top to bottom.

The difficulty lies in tying into the existing drain. Using the most logical (to me) drain design in the addition, I have a 22.5' of horizontal run (shown in "new mudroom" above, longest run is from washer). I have an additional 25' of horizontal run from the edge of the addition through the existing crawlspace to get to the nearest existing drain, a 4" horizontal. (I've looked at going outside and tying to the sewer, but the run is far too long vs. available height).
In addition to the long overall run length, I have a relatively shallow crawlspace: 18.75" from the bottom of the existing joists to the top of the 4" existing drain. To further complicate matters, the new joists are 8.5" lower than the existing joists.
Below is the plan I have worked out (sorry for flipping the layout 180 degrees in the below drawing). I think I have the drops correct (I literally have ZERO extra vertical available with this plan, hence the wye on it's side). I think it's really too much to visualize (go for it if you're a spatial ninja!) so what I most want feedback on are if the fittings I have shown are OK. In particular, the only way this can work is if the 4"-4"-2" wye is on it's side-- is that allowed?
I also need some guidance on where I should put cleanouts. The addition crawlspace with technically be accessible, but it will be a major PITA, so consider it unaccessable.

Many, many thanks in advance for feedback and I promise to pay it forward if/when I learn enough to give good feedback to others.
Matt
I've been lurking for months as we planned our renovation, and the framers have our addition to the point where I need to get my rough-ins done. I've worked up the following from what I've read here and my reading of the code. I'd really appreciate any feedback-- it's easy for a beginner like me to get the wrong fitting...
Some background. The house is a 1910 Florida Craftsman that's long suffered at the hand of the unpermitted DIYer. I'm cleaning up issues as fast as I can, but in the meantime we're adding a garage and laundry room. In the laundry, we'll have a sink and washer, so I'm planning to size drains @ 2" for the 4 DFUs. In both sketches below the joists run from top to bottom.

The difficulty lies in tying into the existing drain. Using the most logical (to me) drain design in the addition, I have a 22.5' of horizontal run (shown in "new mudroom" above, longest run is from washer). I have an additional 25' of horizontal run from the edge of the addition through the existing crawlspace to get to the nearest existing drain, a 4" horizontal. (I've looked at going outside and tying to the sewer, but the run is far too long vs. available height).
In addition to the long overall run length, I have a relatively shallow crawlspace: 18.75" from the bottom of the existing joists to the top of the 4" existing drain. To further complicate matters, the new joists are 8.5" lower than the existing joists.
Below is the plan I have worked out (sorry for flipping the layout 180 degrees in the below drawing). I think I have the drops correct (I literally have ZERO extra vertical available with this plan, hence the wye on it's side). I think it's really too much to visualize (go for it if you're a spatial ninja!) so what I most want feedback on are if the fittings I have shown are OK. In particular, the only way this can work is if the 4"-4"-2" wye is on it's side-- is that allowed?
I also need some guidance on where I should put cleanouts. The addition crawlspace with technically be accessible, but it will be a major PITA, so consider it unaccessable.

Many, many thanks in advance for feedback and I promise to pay it forward if/when I learn enough to give good feedback to others.
Matt