PDA

View Full Version : please assist dwv setup.....



hman
10-22-2005, 08:18 PM
Awesome forum.

Hope you guys could help me out. Im trying to help out a friend with setting up his dwv setup in his bathroom and was hoping you could point me in the right direction. Here are a couple of pics that I took. Which one would be the correct setup? Please, if were totally off, let us know which way is correct

Terry
10-23-2005, 12:57 AM
None of those would work if you are using the UPC code.

hman
10-23-2005, 06:44 AM
Thanks for your reply.
Could someone please explain the best way to set this up. Any suggestion is greatly appreciated.
Thanks.

hj
10-23-2005, 07:45 AM
There could be several "correct" ways to do it, you just picked two that were not. One of the biggest corrections is that you cannot have the toilet flowing past the shower connection, unless you have a vent between the shower trap and the 3" connection. Other items, such as how you vent the toilet would depend on how lenient the inspector was that day, but most would not allow the vent to continue horizontally after the toilet opening.

hman
11-05-2005, 10:40 PM
What's up everyone.....

Now that the hurricane is going and have power we could now finish this project. Could you please take a look and tell us what you think. Please.

Thanks....

sulconst2
11-06-2005, 09:12 AM
you haven't addressed post #4. vent the shower and roll the toilet vent.

hman
11-10-2005, 12:38 PM
Could you guys tell me which would be the correct way to set this up.....
Thanks in advance.....

01sesedan
12-28-2005, 01:10 PM
Hope everyone had a great Christmas.

I think I got it this time.

How about this setup.

We are planning on moving the 3' main from the left side to the right side.

I hope the picture makes sense.

Thanks.....

01sesedan
12-30-2005, 07:09 PM
New drawing, it's a little rough but I hope it makes .

FloridaOrange
12-30-2005, 08:06 PM
Is the circle where the water closet will go? At the end of your 2" line your lavatory with a a branch off to pick up the shower?

That's how I see it and if those answers are yes then your system will work.

Dunbar Plumbing
12-31-2005, 07:11 AM
I cannot follow the stick drawing but if that picture is followed the way you have the fittings laid out, in about 1 to 3 years the vents are going to seal up since you are flat venting under 42". Not acceptable. Groundwork when it comes to plumbing is crucial, otherwise the alternative is years of drain problems........

hman
12-31-2005, 11:44 PM
Hope this drawing makes more sense.
Thank for your replies..

Happy New Year..

sulconst2
01-01-2006, 01:31 PM
looks right. imo. make sure to roll your your vents upward. p trap for shower must be glue type. when connecting vents pitch upward and increase pipe size thru roof.

hman
01-01-2006, 09:09 PM
Here's a view of the vents going up the wall.
Hope this one makes sense.

01sesedan
01-04-2006, 02:26 PM
So, what do you guys think?

hman
01-09-2006, 01:31 PM
So, would this be the correct setup?

Thanks........

Dunbar Plumbing
01-09-2006, 02:39 PM
If you didn't address the flat venting issue, NO. A stick drawing isn't addressing your issue. Like I stated before, hire a plumber to get the ground work right. Otherwise figure a drain cleaning machine as part of the project.

hman
01-09-2006, 09:04 PM
Thank You.